LaPorte Substation

Laporte Substation Expansion


In 2016, Platte River completed a 230kV expansion and autotransformer addition project at Laporte Substation, located northwest of Fort Collins. Completion of this substation expansion increased Platte River’s power transmission capacity from Rawhide Energy Station by 41 percent. This increased power transmission capacity helps Platte River to provide a more reliable and robust power supply to our owner municipalities. Installation of a second 230/115kV autotransformer helps Platte River to minimize system exposure and risks during maintenance operations or contingency situations. Several equipment and protection upgrades were also completed during this project to increase system reliability and more effectively protect our assets. The oil containment plan for the existing autotransformer was improved and existing oil circuit breakers were replaced.

  • Over 9,600 hours invested by Platte River
  • Total of 10 departments involved
  • Project took over 22 months to complete
  • Over 18 miles of control cable installed
  • Over 200 foundations installed

Projects like this one help Platte River achieve operational excellence by designing, constructing, operating, and maintaining safe, reliable, and environmentally-responsible transmission assets.

laporte constructionFoundation Installation

laporte constructionNew 230 115kV Autotransformer